2017-2019
 Discussions with WPD about need for new courts
Submit extensive market/feasibility study to WPD
Set aside reserves annually to help pay for new courts

Winter 2019
Formal planning with WPD Begins

Spring-Summer 2020
Initial Drawings Reviewed
Agreement by WPD to move Chipping Green and build courts on West side of Hut
Easement issues with Cell Tower identified

June 2020
Contract Signed with Total Platform Tennis to Construct Courts
$40,000 Deposit provided by WPTC

Fall 2020 – Spring 2021
Multiple Planning Meetings with WPD

Spring 2021
APTA and CPTC Grant Requests Submitted
APTA and CPTC Grants Approved in May 2021
Winnetka Platform Tennis Center Master Plan Approved by WPTC and Submitted to WPD

June 2021
Expected Approval of Winnetka Platform Tennis Center Master Plan by WPD

August 9, 2021
Expected Approval of Special Use Permit by Village Zoning Board

PHASE 1

June 15, 2021
Launch Fundraiser

July 1, 2021
Deadline for extended membership bids
2021-22  Registration opens

Summer 2021
Finalize all architectural/site drawings, Submit all permits

August/September 2021
Finalize permitting

Fall 2021
Break ground & build courts

PHASE 2

2021-2
Complete outdoor decking

PHASE 3

TBD
Plan for & build hut extension